You may not need permission at all
A good number of extensions and loft conversions are permitted development, meaning you
can build without applying. The limits are specific, and they are easy to breach by a few
hundred millimetres. The dimensional limits are on the
rear extensions and
loft conversions pages.
Larger single storey rear extensions can go through prior approval
instead: a lighter route where the council notifies your neighbours and decides within
42 days rather than assessing the design in full.
Those rights disappear in conservation areas, on listed buildings, on flats and
maisonettes, where an Article 4 direction applies, and where previous owners have already
used the allowance up. We check which of those applies to your address before anything
gets drawn.
Worth having anyway
Where work is permitted development, a lawful development certificate is still worth
having. It is proof for your buyer’s solicitor in ten years’ time.
What a good application contains
- Location plan and site plan to a recognised scale, correctly annotated.
- Existing plans, elevations and sections, drawn from a survey of the house as it
really is rather than from the estate agent’s floorplan.
- Proposed plans, elevations and sections that agree with each other in every
dimension.
- A design and access statement where one is required, arguing the scheme against the
policies the officer has to apply.
- The correct application forms, ownership certificates and fee.
Half of that list is administrative. It is also where applications sit at validation for
weeks before anyone looks at the design.
See a drawing set that answers it.
Pre-application advice, and when it is worth the fee
Most councils will give you a written view on your scheme before you apply, for a fee.
It is not binding, but on a marginal scheme it is usually the cheapest money you will
spend.
It earns its fee when the scheme is bigger than the neighbours’ precedent, in a
conservation area, near a listed building, or where a previous application has failed.
Rarely for a modest rear extension that clearly fits policy.
How long it takes
Statutory determination periods
| Route | Statutory period |
| Householder application | 8 weeks |
| Larger home extension, prior approval | 42 days · 21 days for neighbours |
| Full application, larger schemes | 13 weeks |
The clock starts at validation, not at submission, which is why an incomplete
application is expensive in a way that is not obvious at the time. Once granted,
permission normally has to be started within three years.
Which council decides
Local planning authority by area
| Where | Authority |
| Maidstone, Bearsted | Maidstone Borough Council |
| Aylesford, West Malling, Tonbridge | Tonbridge and Malling Borough Council |
| Sittingbourne | Swale Borough Council |
They apply national rules through different local plans, and their policies on extension
size, roof form and materials are not identical. Knowing which document your scheme is
judged against matters more than knowing anyone at the council.